Latest News

Council has appointed a contractor to manage the subdivision and civil construction for the Erskine Park Urban Reinvestment Project. Civil construction is an essential step to prepare the land for future home construction by connecting services to the site such as sewer, electricity and communications.

The contractor, Masport, will be constructing fourteen residential lots as per the subdivision Development Application approvals. Construction is scheduled to commence in 2024.

Public Open Space Upgrades

Chameleon Reserve $300k in tree planting

Chameleon Reserve amenity and storage building

Footpath upgrades

Phoenix Reserve upgrade

Phoenix Reserve waterplay

Phoenix Reserve upgraded waterplay view 1

Phoenix Reserve upgraded waterplay view 2

Skylark Reserve upgrade

Skylark Reserve upgrade by Penrith City Council

Spica Reserve Upgrade

Spica Reserve upgrade by Penrith City Council view 3

Spica Reserve upgrade by Penrith City Council view 4

Capella Reserve upgrade by Penrith City Council

Capella Reserve redevelopment sculpture

Capella Reserve upgrade

Erskine Park Urban Reinvestment Timeline

orange tickfinal

 Detailed planning and design for each site: February – September 2019

orange tickfinal

 Preparation of design guidelines and subdivision plan: 2020

orange tickfinal

orange tickfinalNew Detailed Site Investigations: March - June 2021

orange tickfinal DA submission: January 2022

orange tickfinal DA Approval: Q4 2022

orange tickfinal Detailed civil and servicing design: 2023

orange tickfinal Civil construction contractor appointed: Mid 2024

orange outline circle2Subdivision and civil construction commences: late 2024

orange outline circle2 Marketing and sales: 2024-2025